Updates

09/21

Due to weather expected tomorrow, Thursday, 09/22, work will not take place tomorrow. We will have crews return on Friday, 09/23, weather permitting. This shouldn't impact the overall schedule of the project as we expect to move onto the next buildings on Monday, 09/26 as expected (weather permitting).


09/19

Today we will be beginning on buildings labeled 4, 5, and 6. If you have any questions, please contact your management company or Capital Construction at 952-222-4004 or at info@capitalmn.com. 


09/16

We are finishing up the first three buildings. Thanks everyone for your cooperation. 


09/15

Today we will be delivering and lifting materials onto the buildings numbered 4, 5, and 6. 


09/12

We are officially beginning the project today! We will be starting on buildings labeled 1, 2, and 3. If you have any questions, please contact your management company or Capital Construction at 952-222-4004 or at info@capitalmn.com. 


09/10

Please refer to the building map for reference on which buildings will have materials delivered and boomed each week throughout the project. This schedule is weather permitting.

09/10 - Week 1: Buildings 1, 2 and 3

09/17 - Week 2: Buildings 4, 5, and 6

09/24 - Week 3: Buildings 7, 8, and 9

10/01 - Week 4: Buildings 10, 11, and 12

10/08 - Week 5: Buildings 13, 14, and 15


Timing

In the coming weeks Capital Construction will be assisting with insurance claim approved roof replacements throughout your community. This includes all buildings. We will begin with the buildings labeled 1, 2, and 3 then move onto buildings labeled 4, 5, and 6, and so on and so forth finishing with the final building labeled 13, 14, and 15.

We expect to begin the project, weather permitting, on Monday, September 12.

We will have 3 crews working onsite and estimate each building to take approx. 5 days to complete, weather permitting. The entire project should wrap up in about 5 weeks, weather permitting.

Working hours are Mon.-Sat., 7:00am-dusk.

Please look over the attached documents regarding pre-project measures which should be taken, information on what to expect throughout the project, and a map of the building order in which the roof replacements will be completed.

Please contact us should you have any questions or concerns.

We look forward to servicing your community and thank you in advance for your patience throughout the project as well as your cooperation with the relative disruptions as a result!


Site Map



What To Expect

There will be disruptions and required accommodations to be made by residents.  We appreciate your patience throughout the project and your understanding as we work through repairs. 

As with any large construction project, some issues are anticipated.  Please report them to us as soon as possible so we can address accordingly. 


Vehicles

VERY IMPORTANT: Have your vehicles off the driveway and moved away from your building by 7:00 AM on the day(s) listed above to prevent damage to vehicles. 


Suggestions to Ensure a Problem Free Roof

  • Remove patio furniture, grill and property from decks/patios as well as fragile items from walls, as these may incur damage during work. Contractor is NOT liable for such damages.
  • All pet waste needs to be removed before the project starts. Messes as a result are not the responsibility of the contractor. 
  • While we are working on your home, please close your window coverings during the day. This will help avoid any accidental embarrassments as the workers go up and down ladders to access the roof.

Landscaping

If there are any special or delicate plant or shrubs, please notify us of them before the job starts and we will protect them as best as possible.


Clean Up

One of the most important aspects of a project is keeping the area clean during the job. Here is how we strive to do this every day...

  • Clean your site during the day and at the end of the day.
  • Clean your lawn and site with our magnetic “nail-finder” to reduce chance of any nails being left in your lawn.
  • Keep our tools and materials neatly organized and out of the way.


Conditions Beyond Our Control

Please be aware that despite our best efforts the following may occur during improvement projects, and are not the responsibility of the contractor:

  • Existing structural problems: Such as loose or cracked plaster and drywall, sagging rafters, nail-pops, bowed walls, previously rotted or damaged materials, etc.
  • Scheduling difficulties: We do our best to stay on schedule, but mother nature and other emergencies can lead to delays. We will do our best to limit delays.


Questions?

Please do not hesitate to contact Capital Construction LLC with any questions or concerns via the website form on this page, or by contacting our Director of Multifamily Operations Derek Muelken directly at (952) 222-4004 or at info@capitalmn.com. Please leave your address, name, email and phone number when you contact us. Thank you!


Additional References

What to Expect

4.9 out of 5
Out of 828 Google Reviews
Capital Construction, LLC BBB Business Review
Owens Corning Logo
Gold Award
Silver Award
Get Started Now

Request appointment?