Thornbury Homeowners Association
Update 2/19/25
Siding replacements are underway with buildings 1-5, 10-28, 29-44, 46-50 complete and buildings 45, 51-53 underway! With the weather today we had to pull off the jobsite, but we will continue working as soon as weather permits. We will be working through the weekend to catchup due to lost time this week as a result of weather (Sunday included). We expect to complete all buildings in the next 2 weeks.
Update 2/18/25
With the weather today we are NOT working onsite. Tomorrow’s forecast looks unfavorable as well so we may not be able to work tomorrow, however we will continue working as long as weather permits and intend to work through the weekend to catch up.
Update 2/12/25
Siding replacements are underway with buildings 1-5, 15-17, 26-36 complete and buildings 18-20 and 42-49 underway! With the weather coming today we may need to pull off the jobsite for a bit, but we will continue working as long as weather permits. We expect to wrap up the larger buildings in the next day or so and are shooting to complete all buildings in the next 2 weeks.
Update 2/7/25
Siding replacements are underway with buildings 29-36 complete! We are currently wrapping up buildings 37-41 and expect to finish those today. In addition, we’re working on buildings 1 and 2 and once complete will move onto buildings 3 and 4, then 5-6 and so on and so forth until buildings 1-28 are complete. Once those are complete we will move back over to buildings 42-49 and continue through the remaining buildings until complete. Weather permitting, we expect to finish buildings 1-28 by the end of next week.
If you have a satellite dish on the siding slated for replacement which you are NOT using and wish for us to remove and dispose of it please contact us by emailing josief@poweredbystronghouse.com.
Screen replacements will be scheduled after siding repairs are complete which will wrap up the entire project.
Update 2/4/25
Siding replacements have been started with materials delivered onsite! We will be moving some siding materials over to the grassy area by building 14 (near 833 Brookmead) to accommodate the delivery of items onsite, and as marked with an “X” on the map provided below. Once we get through the first couple of buildings we will have a better idea how quickly we expect to move through the project.
We will be starting on buildings 29, 30 and 31, through building 120 then moving to buildings 1-28 until all buildings are complete. We appreciate your patience and understanding as this work develops and if changes are needed to the original order/plan.
Garage door replacements are complete. Screen replacements will be scheduled after siding repairs are complete which will wrap up the entire project.
Update 1/10/25
Siding installation update and guide:
We will be starting the siding replacements the week of Feb. 3rd, weather permitting!
Materials will be delivered and staged throughout the development on Mon. Feb. 3rd with siding replacements starting Tues. Feb. 4th.
We will be starting on buildings 29, 30 and 31, through building 120 then moving to buildings 1-28 until all buildings are complete. We expect to have 3 crews onsite and each crew should be able to finish a building in 1-3 days, weather permitting. Please note not all buildings are receiving new siding and not all elevations per building are being replaced, only select buildings and elevations in accordance with the approved insurance scope.
The entire siding portion of the project should wrap up in 6-8 weeks, weather permitting.
In addition, I've attached a map showing some additional detail on building numbers and staging locations (marked with a red "X") for materials, bathrooms and equipment.
Please reach out with any questions or concerns.
Refer to the attached documents for more information:
SIDING INSTALLATION NOTICE 📄
Insurance claim Replacement Project Details:
Update 12/19/24
Siding replacements will be scheduled in the coming weeks as material availability is confirmed. Thank you for your patience on this as we navigated the coverage with the insurance carrier. More information to come.
Update 11/4/24
Garage door replacements, per the insurance scope, are underway. Overhead Door will contact each resident to schedule their door replacement.
Update 10/2/24
Gutter and downspout replacements are complete.
Update 9/23/24
Gutter and downspout replacements are nearly complete. We have 11 buildings remaining, however with the rain today we weren’t able to complete any therefore we will return tomorrow, weather permitting, to complete buildings 109-112. We will move onto buildings 113-116 Wed. and the final four buildings, 117-120, will wrap up Thurs./Fri., weather permitting. We are still working with insurance regarding the siding repairs and once we have that finalized we can order materials and work on scheduling the remaining repairs.
Update 9/16/24
Gutter and downspout replacements are underway. We are complete through building 92 and are currently working on buildings 93-96. We expect to complete 4 buildings per day and will move onto buildings 97-100 next.
Update 9/10/24
Gutter and downspout replacements are underway. We are complete through building 73 and are currently working on buildings 74-77 as well. We will move onto buildings 78-81 tomorrow and buildings 82-85 on Thursday and on Friday moving onto buildings 86-89, all weather permitting. Next week we should start gutters and downspouts on buildings 90-93, weather permitting. We are still working with insurance on siding scope and once there’s resolution on that we will proceed with ordering materials and scheduling.
Update 9/4/24
Gutter and downspout replacements are underway. We are complete through building 62 and are currently working on buildings 63-66 as well. We will move onto buildings 67-70 tomorrow and buildings 71-74 on Friday, all weather permitting. We are still working with insurance on siding scope and once there’s resolution on that we will proceed with ordering materials and scheduling.
Update 8/30/24
Gutter and downspout replacements are underway. We are complete through building 54 and are currently working on buildings 55-58 as well. Next week Tues. we will move onto buildings 59-62, weather permitting. We are still working with insurance on siding scope and once there’s resolution on that we will proceed with ordering materials and scheduling.
Update 8/26/24
Gutter and downspout replacements are underway, however the heat has set us back a bit. We are complete through building 42 and are working on building 43 today as well. Tomorrow we will move onto buildings 44-48 tomorrow and will move onto buildings 39 and 43 Thurs. With buildings 44-48 starting Friday, weather permitting.
Update 8/20/24
Gutter and downspout replacements are underway. We are complete through building 33 and will be working on buildings 34-38 tomorrow (we won’t be onsite today) and will move onto buildings 39 and 43 Thurs. With buildings 44-48 starting Friday, weather permitting.
Update 8/13/24
Gutter and downspout replacements are underway. We are complete through building 23 and are currently working on buildings 24-26 and will move onto buildings 27 and 28 in the coming days. We expect to finish all townhome buildings by the end of the week and will then move onto the single family homes starting next week Mon. (starting with building 29).
Update 8/6/24
Gutter and downspout replacements are underway. We will be complete through building 16 by the end of the day and will move onto buildings 17-19 tomorrow.
Update 8/2/24
Gutter and downspout replacements are underway. We will be complete through building 13 by the end of the day and will move onto buildings 14-16 on Monday.
Update 7/30/24
Gutter and downspout replacements are underway. We are complete through building 7 and should wrap up buildings 8 and 9 today or tomorrow, weather permitting, and will then move onto buildings 10 and 11.
What to expect:
We expect each building to take approx. 1 day to complete. We will have 3 crews working onsite and each on different buildings. We expect EACH crew will be able to complete 1.5 TOWNHOME buildings per day and 3 SINGLE FAMILY HOMES per day, weather permitting. We believe we will wrap up with all roof replacements in 4-5 weeks, again weather permitting.
There will be disruptions and required accommodations to be made by residents. We appreciate your patience throughout the project and your understanding as we work through repairs.
As with any large construction project, some issues are anticipated. Please report them to us as soon as possible so we can address accordingly.
Vehicles * VERY IMPORTANT *
Have your vehicles off the driveway and moved out and away from your garage and building by 7:00 AM on the day(s) listed above to prevent damage to vehicles.
Suggestions to Ensure a Problem Free Roof
Remove patio furniture, grill and property from decks/patios as well as fragile items from walls, as these may incur damage during work. Contractor is NOT liable for such damages.
Please remove pet waste from your yard before the project starts to avoid messes on the roof and sidewalks, etc. as a result.
While we are working on your home, please close your window coverings during the day. This will help avoid any accidental embarrassments as the workers go up and down ladders to access the roof.
Landscaping
If there are any special or delicate plant or shrubs, please notify us of them before the job starts and we will protect them as best as possible.
Clean Up
One of the most important aspects of a project is keeping the area clean during the job. Here is how we strive to do this every day...
Clean your site during the day and at the end of the day.
Clean your lawn and site with our magnetic “nail-finder” to reduce chance of any nails being left in your lawn.
Keep our tools and materials neatly organized and out of the way.
Conditions beyond our control
Please be aware that despite our best efforts the following may occur during improvement projects, and are not the responsibility of the contractor:
Existing structural problems: Such as loose or cracked plaster and drywall, sagging rafters, nail-pops, bowed walls, previously rotted or damaged materials, etc.
Scheduling difficulties: We do our best to stay on schedule, but mother nature and other emergencies can lead to delays. We will do our best to limit delays.
Satellite Dish notice
Homeowners who have satellite dishes will be without service during the re-roofing of your building. Stronghouse Solutions will reset the dish to the best of their ability,
however if you experience issues please notify your service provider to schedule a
service call for recalibration.
If you DO NOT want your satellite dish re-installed once the roof replacement is completed, please contact Josie Flicek before the start of your building by emailing
josief@poweredbystronghouse.com so it can be properly disposed of.
Questions
Please do not hesitate to contact Stronghouse Solutions with any questions or concerns via the website form on this page, or by contacting your account manager, Josie Flicek, at 866.989.6641 or at josief@poweredbystronghouse.com. Please leave your address, name, email and phone number when you contact us. Thank you!